The development comprised the construction of a new 4 storey 500 bedroom hotel. Bedrooms, reception, and gymnasium areas etc. are fully serviced by 2 pipe fan coil units & radiant panels/radiators. AHUs/extract fans, chillers, boilers and generators..
Mechanical and electrical services valued at £8M.
| Client: |
Gratte Manly Limited |
| Location: |
Stansted Airport, Essex |
| Main Contractor: |
Skanska |
| Services provided: |
Commissioning & Water Treatment |
| Project Start date: |
August 2004 |
| Project completion date: |
November 2004 |
|