Nomura Completes on time

Rate this item
(0 votes)

Nomura signed a 20 year lease to occupy the whole of Watermark Place in September 2009. Works on the fit-out of the 500,000 sq.ft office space began immediately. One of our major clients, Michael J Lonsdale, were awarded the reported £25M mechanical services fit-out and began works immediately.

We commenced the extremely ambitious flushing and commissioning programme in April 2010 including 7 day working and 24 hour shifts. Staged handover started in August with the client moving in behind us as we went. Much to everyone's credit, every date has been met. The last two areas of Level 7 and 8 (contractors and storage) will complete by the end of this month with the official handover in January 2011.

Well done to all those involved with particular mention for Darren Claydon and Stuart MacLennan (flushing), Stuart McGeever and Aiden McDonnell (commissioning), Jonathan Carlin and Chris Taylor (commissioning management) without whose dedication and commitment, the project would not have happened.

 

Read 12217 times Last modified on Thursday, 04 October 2012 10:12